Temporary pathway, Pyne & Spelman, Jan 6 - March 29

Outage Period
to
Affected locations
Pyne Hall
Spelman Halls
Outage type
Scheduled
Categories
Sidewalk closure

Facilities will perform stormwater management and bluestone improvements to the pathway between Pyne and Spelman Halls between January 6 and March 29.  A new temporary walkway will be installed and detour signage will be posted accordingly. A flagger will be present to assist with pedestrian movements. Please use caution when in the area. 

Where:    Pathway between Pyne and Spelman Halls
Date:       Monday, January 6, 2025 - Saturday, March 29, 2025
Work Hours:    8AM - 4PM
Impact:    Pedestrian/Sidewalk Detour,  Construction Zone;  Noise

Thank you for your cooperation and if you have further questions, please contact:
Brian Scelza
609.240.9206
[email protected]